Assessments      Building & Zoning  Col.Twp.Flag     Delinquent Taxes Documents Facts&Figures    Financial Info         History     Homestead         Land Division     Maps             Meetings    MobileHomes  NeighborhoodWatch  Officials & Staff Property Taxes Public Safety Roads               Splits & Combos  Township Hall Transfer Station Volunteering     

2000 Road Projects

2000 Road Projects

In 2000, the Columbia Township Board continued to improve Columbia Township roads by paving, graveling, ditching, and other work costing $212,467 in Township funds, $163,759 in Van Buren County Road Commission funds, and $27,545 in Van Buren County funds. See the final figures in the table below for details.

Project
    Road Segment

 

Miles

Est.
Cost

Paving - Second Layer
    47th St. CR380 to 24th Ave.

 

1.00

 

30,502

    54th St. corner of Baseline

0.20

6,440

    CR384 49th St. to CR215

3.00

*101,337

Paving - First & Second Layer
   
47th & 46½ St 16th Ave to CR384


1.25


56,595

Sealcoat
    15th St. CR215 to 52nd St.


1.00


6,950

    52nd St. 15th Ave to CR384

0.76

5,212

    CR215 Baseline to CR388

1.00

*6,974

    CR384 49th St. to CR388

1.84

*12,833

    24th Ave. 50th St. to 46th St.

2.20

15,290

Partial Grading, Drainage, Gravel
    56th St. 8th Ave to CR388


1.25


70,595

Railroad - CR388 Approaches

0.10

*30,070

Culvert - 24th Ave. N Scott Lake

*7,043

Extra Paving Mix - Misc Roads

2,354

Gravel - Miscellaneous Roads

17,800

Ditching - Miscellaneous Roads

7,285

Dust Control - Gravel Roads

19,064

Ditch Mowing - Miscellaneous Roads

5,300

2000 Total

403,771

 

*Van Buren County Road Commission funds

 